Project Description:
The Standards Committee is charged with assembling the criteria for and making the recommendations regarding spaces, materials and color palettes with respect to accessibility, durability and sustainability. The committee will coordinate with all other programming committees and its recommendations will have a bearing on all projects in the Master Plan.

Project Updates

Date
Update
March 13, 2015 New atrium door installation started March 13; to be complete next week.

Landscaping work will be done this spring.
March 6, 2015 We have been waiting for warmer weather to install the new door into the T Building courtyard. Weather permitting; the door will be installed on 3/13.

Landscaping work will be done this spring.
January 16, 2015 Furniture installation on 1/16.

Atrium Remodel construction is complete.
January 2, 2015 Atrium Remodel construction is in progress; completion anticipated 1/20.

Carpet installation to begin 1/6.

Furniture installation to begin 1/16.
December 12, 2014 Atrium Remodel construction is scheduled to begin 12/23; completion to occur over winter break.
December 5, 2014 Atrium Remodel construction anticipated December 2014.

Campus Signage Standards programming kick-off meeting held on 12/3.
November 21, 2014 Atrium Remodel construction anticipated December 2014.
November 14, 2014 Atrium Remodel construction anticipated December 2014.
November 7, 2014 An overview of the Standards package was presented at the CEOC meeting on 11/4.

Visit the Master Plan webpage to view the final Standards package.

Atrium Remodel construction anticipated December 2014.
October 31, 2014 An overview of the Standards package will be presented at the CEOC meeting on 11/4.

Visit the Master Plan webpage to view the final Standards package.

Atrium Remodel construction anticipated December 2014.
October 24, 2014 An overview of the Standards package will be presented at the CEOC meeting on 11/4.

Visit the Master Plan webpage to view the final Standards package.

Atrium Remodel construction anticipated December 2014.
October 17, 2014 An overview of the Standards package will be presented at the CEOC meeting on 11/4.

Visit the Master Plan webpage to view the final Standards package.

Atrium Remodel construction anticipated December 2014.
October 10, 2014 An overview of the Standards package will be presented at the CEOC meeting on 11/4.

Atrium Remodel construction anticipated December 2014.

Programming for the campus-wide Signage Project will begin within the next 2 weeks.
October 3, 2014 The final Standards package is complete and will be uploaded to the Master Plan webpage.

Atrium Remodel renderings were shared at the SGA meeting held on 9/30; construction anticipated December 2014.

Programming for the campus-wide Signage Project will begin within the next 2 weeks.
September 26, 2014 The final Standards package is complete and will be uploaded to the Master Plan webpage.

Atrium Remodel renderings are complete and will be shared with SGA this week.

A Signage Design Consultant for the campus wide Signage Project was approved by the Board on 9/23.
September 19, 2014 The final Standards package will be submitted on 9/26.

Furniture and fabric selections are complete for Atrium Remodel; construction anticipated over Winter Break, December, 2014; please confirm space details for any Spring event reservations in the Atrium with Central Scheduling.
September 12, 2014 Preparation of the Standards package is nearing completion; final comments were received from the Standards Committee and are being incorporated into the Standards package.

The Standards Committee tested seating options for the Atrium Renovation project on 9/10; seating and fabric selections are complete.
September 5, 2014 Preparation of Standards package is nearing completion; Final comments are still needed from the Standards Committee to complete the Standards Package; review of furniture and fabric selections for the Atrium renovation will occur at the Standards Committee meeting on 9/10.
August 29, 2014 Preparation of Standards package is nearing completion; furniture and fabric selections are in progress for the Atrium renovation.
August 22, 2014 Preparation of Standards package continues.

Reminder: Comments are needed from Standards Committee to complete Standards Package.
August 15, 2014 Preparation of Standards package continues.

Reminder: Comments are needed from Standards Committee to complete Standards Package.
August 8, 2014 College’s Standards is in progress; committee comments are being solicited; complete Standards package due in August.

Reminder: Comments are needed from Standards Committee to complete Standards Package.
August 1, 2014 College’s Standards is in progress; committee comments are being solicited; complete Standards package due in August.
July 18, 2014 Office Furniture finishes and atrium carpet tile approved; review of stairwell finishes in progress.

Revised draft of College’s Standards is in progress; completion anticipated end of July.
July 11, 2014 A draft of the College’s Standards is in progress; completion anticipated end of July.
June 20, 2014 Furniture concepts and color selections are being evaluated for common areas.

Committee Meetings

Meeting Date
Minutes (PDF)
July 16, 2014 Minutes
April 9, 2014 Minutes
February 17, 2014 Minutes
November 4, 2013 Minutes
October 7, 2013 Minutes
September 23, 2013 Minutes