Project Description:

The Classroom Modernization project encompasses mockups as well as classrooms upgrades across campus. The mockups will incorporate information developed by the Classroom and Standards Programming Committees and transform the data into how our classrooms will look and function in the future. Four classrooms and one computer lab will be converted during this process and will allow us to receive feedback from faculty to make improvement in future designs. During A&B Remodel it is the intent of the college to upgrade as many classrooms as possible based on the standards developed through these mockups.

Budget: $3,200,000 

Construction Schedule: May 2016–August 2017

Square footage of new construction: N/A

Square footage of renovated area: N/A

Project Updates

Date
Update
September 26, 2014 The Classroom Mockups are in use.

Your feedback is important and will be considered during the design phase for all classrooms. Please provide your feedback.
September 19, 2014 The Classroom Mockups are in use.

Your feedback is important and will be considered during the design phase for all classrooms. Please provide your feedback.
September 12, 2014 The Classroom Mockups are in use.

Your feedback is important and will be considered during the design phase for all classrooms. Please provide your feedback.
September 5, 2014 Training on new technology equipment is complete and the Classroom Mockups are currently in use.

Please stop by the Classroom Mockups and provide your feedback.
August 29, 2014 AV programming is complete; training on new technology equipment is in progress for Classroom Mockup faculty.

Please stop by the Classroom Mockups and provide your feedback.
August 22, 2014 AV installation is complete and AV programming is nearing completion.

The Classroom Mockup Open House was held Tuesday, 8/19; Please stop by the Classroom Mockups and provide your feedback.
August 15, 2014 Furniture delivery is complete; AV installation continues and is nearing completion.

Mockup rooms are: C131; C132 (Furniture only); C133 (Furniture only); C134 and L113.
August 8, 2014 Classroom Mockup Construction is complete.

Furniture delivery is in progress and nearing completion.

AV installation is in progress and to occur through 8/22.
July 25, 2014 Classroom Mockup Construction to be completed by August 8.

Furniture delivery begins next week.

AV installation to occur through 8/22.
July 18, 2014 Classroom Mockup Construction in progress 6/2 – 8/11.

Painting is complete in L113; light fixtures install is complete in C131 and L113.

Available for Classes - Fall, 2014.

Furniture installation to begin – 8/4.

AV installation to occur through 8/22.

Reminder - No unauthorized access is permitted in construction areas.
July 11, 2014 Classroom Mockup Construction in progress 6/2 – 8/11.

Painting and ceiling grid installation is complete.

Carpet and vinyl tile installation is complete in C131 and C134.

Door and hardware installation is complete.

Available for Classes - Fall, 2014.

Furniture installation to begin – 8/4.

Notice of Award for Classroom AV - 7/2.

AV installation to occur through 8/22.

Reminder - No unauthorized access is permitted in construction areas.
June 27, 2014 Classroom Mockup Construction begins 6/2 – 8/11.

Available for Classes - Fall, 2014.

Furniture installation to begin – 8/4.

Classroom AV Board Recommendation approved - June 24th Board Meeting.

AV installation to occur through 8/22.

Reminder - No unauthorized access is permitted in construction areas.
June 20, 2014 Classroom Mockup Construction begins 6/2 – 8/11.

Available for Classes - Fall, 2014.

AV Board Recommendation for Award - June 24th Board Meeting.

Reminder - No unauthorized access is permitted in construction areas.
June 2, 2014 Classroom Mockup Construction begins 6/2 – 8/11.

Available for Classes - Fall, 2014.

Bids for AV due – 6/12.

Construction signage will be posted in affected areas.

No unauthorized access is permitted in construction areas.
May 16, 2014 Construction for Classroom Mockups to start June, 2014.

Available for Classes - Fall, 2014

Insufficient bids received for AV installation; to be re-bid 5/22.
May 9, 2014 Bids for AV were received on 5/8
May 2, 2014 Classroom Mockups:
Construction for Classroom Mockups - Summer, 2014

Available for Classes - Fall, 2014

Bids for furniture were received on 5/1

Bids are due for AV on 5/8
December 20, 2013 The Classroom Modernization Programming Committee attended a site visit at the Merchandise Mart in Chicago on 12/16. Construction (for mockups) is scheduled to coincide with the spring intersession or summer session.
December 13, 2013 The Classroom Modernization Programming Committee will be attending a site visit at the Merchandise Mart in Chicago on 12/16. Construction (mockups) is scheduled for spring 2014.
October 25, 2013 The Classroom Committee attended the Flexible Learning Spaces Seminar at the University of Illinois Urbana-Champaign on 10/22.
October 18, 2013 The Classroom Committee will be attending the Flexible Learning Spaces Seminar at the University of Illinois Urbana-Champaign on 10/22.
October 11, 2013 The Classroom Committee will be attending the Flexible Learning Spaces Seminar at the University of Illinois Urbana-Champaign on 10/22.
October 4, 2013 The Classroom Programming Kick-Off was held on October 4, 2013.
Construction start (Mockups) Spring 2014.
September 30, 2013 Programming starts October 2013.
Construction start (Mockups) Spring 2014.
September 23, 2013 Programming starts Fall 2013.
Construction start (Mockups) Spring 2014.

Committee Meetings

Meeting Date
Minutes (PDF)
Classroom Technology
December 20, 2013 Minutes
Programming Committee
December 6, 2013 Minutes
November 15, 2013 Minutes
October 4, 2013 Minutes