Campus Core Projects

Project Description:

The Core projects focus on renovations to the Main Lobby - the checkerboard court, connecting link and atrium, as well as the addition of a new cafeteria building. The new cafeteria will be located west of the main lobby overlooking Willow Lake. During this project the checker board court will be covered and combined with the two lecture hall spaces to create a new bookstore and a new student activities office. These new and renovated spaces will also utilize the geothermal heating and cooling along with LED lighting to maximize energy efficiency.

Budget: $23,221,996

Construction Schedule: June 2015–July 2016

Square footage of new construction: 11,878 (Cafeteria, Servery, Kitchen/Support) + 4,770 (Checkerboard Court portion of Connecting Link, Bookstore and Student Activities)

Square footage of renovated area: 11,000 (Main Lobby, Bookstore and Student Activities)

Watch the demolition of the Main Lobby staircase that was performed using a robot.


Project Updates

Date
Update
October 28, 2016 B-wing elevator repairs are complete. Elevator inspection scheduled.

Temporary landscaping work has begun. The blanket and seeding is to protect the site from winter conditions until final landscaping can take place next year.
October 21, 2016 B-wing elevator repairs are complete. Elevator inspection scheduled.

Temporary landscaping work to begin soon to protect the site from winter conditions.
October 14, 2016 B-wing elevator repairs are nearing completion.

Temporary landscaping work to begin soon to protect the site from winter conditions.
October 7, 2016 Exterior handrail installation is nearing completion.

B-wing elevator repairs are nearing completion.

Temporary landscaping work expected through mid-October.
September 30, 2016 Exterior handrail installation is ongoing.

Light pole installation is complete.

B-wing elevator to remain closed for necessary repairs to existing systems.

Temporary landscaping work expected through mid-October.
September 23, 2016 Exterior handrail installation is ongoing.

Light pole installation continues.

B-wing elevator to remain closed for necessary repairs to existing systems.

Temporary landscaping work has begun.
September 16, 2016 Exterior handrail installation is ongoing.

Pouring bases for site lighting began this week. Light pole installation to begin next week.

B-wing elevator to remain closed for necessary repairs to existing systems.

Temporary landscaping work also scheduled to begin next week.
September 9, 2016 Furniture installation is underway.

B-wing elevator to remain closed for necessary repairs to existing systems.

Commissioning of mechanical units in Central Plant continues.
September 2, 2016 Furniture installation is underway.

B-wing elevator to remain closed for necessary repairs to existing systems.

Commissioning of mechanical units in Central Plant continues.
August 26, 2016 Furniture installation is underway.

B-wing elevator to remain closed for necessary repairs to existing systems.

Commissioning of mechanical units in Central Plant continues.

Café is open.
August 19, 2016 Furniture installation is underway.

Final elevator inspection is scheduled for early next week for the renovated B-wing and new food service elevators.

Commissioning of mechanical units in Central Plant continues.

Café is open.
August 12, 2016 Furniture installation is underway.

Cafe Health Department Inspection is complete.

Commissioning of mechanical units in Central Plant continues.

Equipment has been relocated into the new Willow Café.

Café scheduled to be operational for Monday, August 15.
August 5, 2016 Furniture installation is underway.

Blackout testing for emergency and life safety systems was conducted Friday.

Cafe Health Department Inspection is complete.

Commissioning of mechanical units in Central Plant continues.

Move-in coordination is in progress for Fresh Ideas.

Café scheduled to be operational for Fall Semester.
July 15, 2016 Kitchen equipment installation and hookup is nearing completion; testing to begin next week.

Terrazzo polishing is complete.

Sprinkler testing and fire department walkthroughs continue.

Commissioning of mechanical units in Central Plant is ongoing.

Final interior painting and tile finishing work is underway.

Construction to be completed July 25. New equipment training to be conducted afterward. Scheduled to be open Fall Semester.
July 8, 2016 Kitchen equipment installation and hookup is underway.

Terrazzo polishing is nearly complete.

Sprinkler testing and fire department walkthroughs being conducted all this month.

Commissioning of mechanical units in Central Plant is ongoing.

Final interior painting and tile finishing work is underway.

Construction to be completed July 25. New equipment training to be conducted afterward. Scheduled to be open Fall Semester.
July 1, 2016 Kitchen equipment installation and hookup is underway.

Terrazzo work continues. Polishing infill court done. Core is underway.

Sprinkler testing and fire department walkthroughs being conducted all this month.

Pre-functional testing of mechanical units in Central Plant is nearing completion, commissioning to follow.

Final interior painting and tile finishing work is underway.

Construction to be completed July 25. New equipment training to be conducted afterward. Scheduled to be open Fall Semester.
June 24, 2016 Kitchen equipment is complete - equipment hookup has begun.

Training is being coordinated for end of July.

Terrazzo work continues.

Sprinkler testing and fire department walkthroughs being conducted all this month.

Pre-functional testing of mechanical units in Central Plant is underway.

Final interior painting and tile finishing work is underway.
June 17, 2016 Kitchen equipment installation continues - large servery items were delivered this week.

Training is being coordinated for end of July.

Terrazzo work continues.

Sprinkler test and fire department walkthrough conducted 6/17/16.

Pre-functional testing of mechanical units in Central Plant is underway.

Final interior painting and tile finishing work is underway.
June 10, 2016 Kitchen equipment installation continues - large servery items were delivered this week.

Training is being coordinated for end of July.

Terrazzo work continues.

Sprinkler test and fire department walkthrough conducted 6/9/16.

Pre-functional testing of mechanical units in Central Plant is underway.

Final interior painting and tile finishing work is underway.
June 3, 2016 Terrazzo work continues in the Core near Connecting Link and A-wing corridors.

Kitchen equipment deliveries began this week, installation is in progress.

Ceiling grid installation in Café is complete, installation in Core areas is complete.

Pre-functional testing of mechanical units in Central Plant is underway.

Final interior painting and tile finishing work is underway.
May 27, 2016 Terrazzo work continues in the Core near Connecting Link and A-wing corridors.

Kitchen equipment deliveries began this week, installation is in progress.

Ceiling grid installation in Café is complete, installation in Core areas is complete.

Pre-functional testing of mechanical units in Central Plant is underway.

Final interior painting and tile finishing work is underway.
May 20, 2016 Terrazzo work nearing completion in new Café.

Installation of exterior metal panels is complete.

Ceiling grid installation in Café is complete, installation in Core areas in progress.

Pre-functional testing of mechanical units in Central Plant has begun.

Final interior painting and tile finishing work is underway.

Fresh Ideas will tour the CLC Learning Farm and meet with Food Service employees.
May 13, 2016 Terrazzo work nearing completion in new Café.

Installation of exterior metal panels is nearing completion.

Ceiling grid installation in Café is complete, installation in Core areas in progress.

Pre-testing of mechanical units in Central Plant has begun.

Final interior painting and tile finishing work is underway.
May 6, 2016 Installation of exterior metal panels is nearing completion.

Ceiling grid installation in Café is complete, installation in Core areas in progress.

Pre-testing of mechanical units in Central Plant has begun.

Final interior painting and tile finishing work is underway.


Operational update:

Fresh Ideas selected as food service management vendor. Vendor will be on site to begin implementation this week.
April 29, 2016 Installation of exterior metal panels is nearing completion.

Ceiling grid installation is in progress.

Pre-testing of mechanical units in Central Plant has begun.

Final interior painting and tile finishing work is underway.


Operational update:

Board tour was held on Tuesday, April 26.
April 22, 2016 Installation of exterior metal panels is nearing completion.

Ceiling grid installation is in progress.

Pre-testing of mechanical units in Central Plant has begun.

Final interior painting and tile finishing work is underway.


Operational update:

The food service selection committee continues through the RFP process.

Board tour scheduled for April meeting.
April 15, 2016 Installation of kitchen hoods is in progress.

Epoxy flooring installation in kitchen area to start next week.

Roof over Infill Court is watertight.

Interior painting and tile finishing work is underway


Operational update:

The food service selection committee continues through the RFP process.

Board tour scheduled for April meeting.
April 8, 2016 Base coat painting has begun in the 2nd floor classrooms.

Roof over Infill Court is 50% complete.

Interior drywall and tile finishing work is underway.

MEP final connections being made in the Central Plant.


Operational update:

The selection committee is continuing through the RFP process; completing site visits for all finalist vendors.

Board tour scheduled for April meeting.
April 1, 2016 Interior drywall and tile finishing work is underway.

Terrazzo flooring work is underway in the core area washrooms.

MEP final connections being made in the new Café basement.


Operational update:

The selection committee is continuing through the RFP process; completing site visits for all finalist vendors.

Board tour scheduled for April meeting.
March 25, 2016 Interior drywall and tile work underway.

Terrazzo flooring work has begun in core washrooms.

Roofing system installation is nearing completion.

MEP final connections being made in the new Café basement.


Operational update:

The selection committee is continuing through the RFP process; completing site visits for all finalist vendors.

Board tour scheduled for April meeting.
March 18, 2016 Exterior curtain wall installation is over 80% complete.

MEP rough-in continues in the new Café basement.

Exterior metal panel installation has begun.

Roofing system installation is in progress.


Operational update:

The selection committee is continuing through the RFP process; completing site visits for all finalist vendors.

Board tour scheduled for April meeting.
March 11, 2016 Curtain wall installation along the south and west facades is underway.

MEP rough-in continues in the new Café basement.

Exterior face brick installation is nearing completion.

Roofing system has started this week due to the mild weather.


Operational update:

The selection committee is continuing through the RFP process; completing site visits for all finalist vendors.

Board tour scheduled for April meeting.
March 4, 2016 Curtain wall installation along the south and west facades has begun this week.

MEP rough-in continues in the new Café basement.

Exterior face brick installation is in progress. The south, west and north facades are complete.


Operational update:

Food service vendors have completed presentations and will continue through the RFP selection process.

The selection committee has representation from all governance groups. Notify your selection committee representative with any questions for the final vendors.

Board tour scheduled for April meeting.
February 26, 2016 Exterior face brick installation is in progress on the North and West facades.

MEP rough-in continues in the new Café basement.

Wall framing continues in the Core area; drywall has begun.


Operational update:

The food service selection committee has Identified 4 vendors to continue through the Final Phase, presentations will be held March 2, 3 and 4.

The selection committee has representation from all governance groups. Please notify your selection committee representative if you have a question for the finalist vendors.

Board tour scheduled for April meeting.
February 19, 2016 Exterior face brick installation is underway.

MEP rough-in is underway in the new Café basement.

Wall framing continues in the Core area.


Operational update:

Food Service Selection Committee is reviewing proposals to determine finalist candidates.

Board tour scheduled for April meeting.
February 12, 2016 Exterior face brick installation is underway.

MEP rough-in is underway in the new Café basement.

Wall framing continues in the Core area.


Operational update:

Food Service RFP was due February 11, 2016. Six vendor proposals were submitted.

Food Service Selection Committee is reviewing proposals to determine finalist candidates.

Board tour scheduled for April meeting.
February 5, 2016 Scaffolding erected, exterior face brick to begin installation next week.

Wall framing continues in the Core area.

Target enclosure for Café building is mid February.


Operational update:

Food Service Selection Committee continues to develop criteria for vendor evaluation.

Food Service RFP due February 11, 2016.

Board tour scheduled for February meeting.
January 29, 2016 Target enclosure for Café building is mid February.

Wall framing continues in the Core area.

Scaffolding to be erected to install exterior finishes.


Operational update:

Successful pre-bid meeting for Food Service contact, good vendor attendance.

Food Service Selection Committee is continuing to identify selection criteria.

Food Service Committee RFP released, due February 11, 2016.

Board tour scheduled for February meeting.
January 22, 2016 Target enclosure for Café building is late January.

Wall framing continues in the Core area.

Floor slab was poured in Main Lobby.

Steel decking is complete for the Infill court.


Operational update:

Food Service Committee RFP released, due February 11, 2016.

Food Service pre-bid meeting is January 28, 2016.

Kick off meeting for the selection committee was held this week.

Board tour scheduled for February meeting.
January 15, 2016 Target enclosure for Café building is mid to late January.

Floor slab in Main Lobby has been poured.

Steel decking is complete for the Infill court.


Food Service Selection Committee activities:

RFP released, due February 11, 2016.

Confirming selection committee members.

Selection committee "kick off" meeting scheduled.
January 8, 2016 Target enclosure for Café building is mid-January.

Mechanical rough-in work in B wing basement is ongoing.

Steel decking is in progress for the Infill court.
January 1, 2016 Target enclosure for Café building is mid-January.

Overhead rough-in work in basement and core is ongoing.

Boilers and air handler for the Café basement have been delivered.

Duct work in A wing corridor on first and second floors to occur over winter break - watch for signs and notices.
December 25, 2015 Exterior steel framing underway. Target enclosure end of month.

Overhead rough-in work in basement and core is ongoing.

Boilers and air handler in basement have been delivered and are in new basement.

Duct work in A wing corridor on first and second floors to occur over winter break - watch for signs and notices.
December 18, 2015 Exterior steel framing underway. Target enclosure end of month.

Overhead rough-in work in basement and core is ongoing.

Boilers and air handler in basement have been delivered and are in new basement.

Duct work in A wing corridor on first and second floors to occur over winter break - watch for signs and notices.
December 11, 2015 Exterior steel framing underway. Target enclosure end of month.

Overhead rough-in work in basement and core is ongoing.
December 4, 2015 Cooling tower above the B wing lecture hall is in place.

Foundations for new elevator in B wing basement work is ongoing.

Structural steel at the roof level is nearing completion.

Structural steel in B159 is underway.

Overhead rough-in work in the core is ongoing.
November 25, 2015 Cooling tower above the B wing lecture hall is in place.

Structural steel nearing completion.

Overhead rough-in work in the core is ongoing.
November 20, 2015 Cooling tower steel erection from Infill Court is underway.

Slab on metal deck poured out on Friday, November 13.

Structural steel nearing completion.

Overhead rough-in work in the core is ongoing.

Saw cutting foundation walls and floors is complete in bookstore area.
November 13, 2015 Slab on metal deck poured out on Friday, November 13.

Structural steel nearing completion.

Overhead rough-in work in the core is ongoing.

Saw cutting foundation walls and floors is complete in bookstore area.
November 6, 2015 Structural steel nearing completion.

Overhead rough-in work in the core is ongoing.

Saw cutting foundation walls and floors is complete in bookstore area.

New concrete block wall is up in the Bookstore. Bookstore remains open.
October 30, 2015 Structural steel erection work began this week.

Overhead rough-in work in the core is ongoing.

New concrete block wall is up in the Bookstore. Bookstore remains open.
October 16, 2015 Foundation and slab on grade pouring scheduled through next week.

Overhead rough-in work in the core is ongoing.

Bookstore remains open in existing location. The book storage area of the store has been relocated to make way for construction.
October 9, 2015 Foundation pouring to continue through next week.

Overhead rough-in work in the core is ongoing.

Drilling for Micro-Piles in the In-fill court is complete.

Demolition work in Tiered Lecture Hall B159, Main Lobby and Checkboard Court complete.
September 18, 2015 Foundation work in the new Café site is in progress.

HVAC ducting rough-in work in the core is underway.

Drilling for Micro-Piles in the In-fill court is complete.

Demolition work in Tiered Lecture Hall B159, Main Lobby and Checkboard Court complete.
September 11, 2015 Foundation work in the new Café site is in progress.

Drilling for Micro-Piles in the In-fill court is underway.

HVAC ducting work on the second floor areas has begun.

Demolition work in Tiered Lecture Hall B159, Main Lobby and Checkboard Court complete.

New directories in place along the temp wall in the Connecting Link to help Fall semester students/faculty navigate safely around construction boundaries.
September 4, 2015 Foundation work in the new Café site began this week.

New directories in place along the temp wall in the Connecting Link to help Fall semester students/faculty navigate safely around construction boundaries.

In-fill court yard excavation underway.

Demolition work in Tiered Lecture Hall B159, Main Lobby and Checkboard Court nearly complete.
August 28, 2015 Demolition complete in the old Admissions/Records vault in B101.

New directories in place along the temp wall in the Connecting Link to help Fall semester students/faculty navigate safely around construction boundaries.

Checkerboard Courtyard excavation underway.

Demolition work in Tiered Lecture Hall B159, Main Lobby and Checkboard Court underway.
August 21, 2015 Robot demolition of main staircase is complete! See video above.

New directories in place along the temp wall in the Connecting Link to help Fall semester students/faculty navigate safely around construction boundaries.

Checkerboard Courtyard excavation underway.

Demolition work in Tiered Lecture Hall B159, Main Lobby and Checkboard Court underway.
August 14, 2015 Robot demolition of main stair is complete! See video above.

Site excavation in progress.

Demolition work in the Main Lobby and Checkboard Court underway.

Geo-foam arrived on site, foam will be used to backfill the main lobby area.
August 7, 2015 Demolition work in the Main Lobby and Checkboard Court underway.

Site work demolition is in progress.

Construction trailer is on site.

Robot demolition of main staircase to start next week. We’ll post a video!
July 31, 2015 Demolition work in the Main Lobby underway.

Site work demolition is scheduled to begin mid-August.

Watch for separate email with updates on traffic and pedestrian routes.
July 24, 2015 Demolition work in the Main Lobby underway.

Site work demolition is scheduled to begin.

Construction trailer is on site.

Watch for separate email with updates on traffic and pedestrian routes.
July 17, 2015 Interior construction barricades in place.

Site work underway, gravel haul road completed.

Construction trailer arrived on July 17.

Watch for separate email with updates on traffic and pedestrian routes.
July 10, 2015 Construction barricades are in place.

Permits were received and subcontractors have been assigned.

Subcontractors approved at the June 23 Board Meeting.

Watch for separate email with updates on traffic, and pedestrian routes.
July 2, 2015 Contractor mobilization began; construction fencing is up, silt fencing, tree removal and installation of construction barricades to follow beginning the evening of Monday, July 6.

Permits were received and subcontractors have been assigned.

Subcontractors approved at the June 23 Board Meeting.

Watch for separate email with updates on traffic, and pedestrian routes.
June 26, 2015 Permits were received and subcontractors have been assigned.

Contractor mobilization will begin June 30 and will include construction and silt fencing, tree removal and installation of construction barricades.

Subcontractors approved at the June 23 Board Meeting.

Watch for separate email with updates on traffic, and pedestrian routes.
June 12, 2015 Scope reviews for the various construction categories are in progress.

Pending permit issuance and subcontractor assignments, Contractor mobilization scheduled for the week of June 15.

Asbestos abatement work for Phase 1 is complete and all-clear testing has been received for all areas. Second Floor B-wing corridor is open.
June 5, 2015 Second Floor B wing Corridor to re-open Tuesday morning, June 9.

Asbestos abatement work for Phase 1 is complete and all-clear testing has been received for all areas.

Pending permit issuance and subcontractor assignments, contractor mobilization scheduled for the week of June 15.
May 29, 2015 Bids received on May 28 and are within budget.

Second Floor B wing Corridor Closed June 1–June 5 for construction-related activities.

Asbestos abatement work continues in various areas. This work is performed in completely contained areas and is done after normal business hours. This work scheduled to complete June 8.

Contractor mobilization scheduled for the week of June 8.
May 22, 2015 Scheduled completion July 2016.

Abatement work is scheduled to begin May 26 and will be in completely contained areas - watch for additional information and notices.
May 15, 2015 Ground Breaking May 16, Noon.

Scheduled completion July 2016.

Associated abatement pre-construction meeting help May 8 - watch for additional information and notices.
May 8, 2015 Ground Breaking May 16, Noon.

Scheduled completion July 2016.

Associated abatement pre-construction meeting help May 8 - watch for additional information and notices.
May 1, 2015 Contract approved at April 23 Board meeting.

Associated abatement contract also approved - watch for additional information and notices.

Ground Breaking May 16, Noon.

Scheduled completion July 2016.
April 24, 2015 Contract approved at April 23 Board meeting.

Associated abatement contract also approved - watch for additional information and notices.

Ground Breaking May 16, Noon.

Scheduled completion July 2016.
April 17, 2015 Contractor's pricing scheduled for approval at the April Board meeting.

Groundbreaking scheduled for May 16.

Projected construction start June 2015.

Café scheduled to open July 2016.
April 10, 2015 Plans have been issued for pricing. Targeting approval at the April Board meeting.

Groundbreaking scheduled for May 16.

Projected construction start June 2015.

Café scheduled to open July 2016.
April 3, 2015 Plans have been issued for pricing. Targeting approval at the April Board meeting.

Groundbreaking scheduled for May 16.

Projected construction start June 2015.

Café scheduled to open July 2016.
March 27, 2015 Plans have been issued for pricing. Targeting approval at the April Board meeting.

Groundbreaking scheduled for May 16.

Projected construction start June 2015.

Café scheduled to open July 2016.
March 13, 2015 Plans have been issued for pricing. Targeting approval at the April Board meeting.

Projected construction start June 2015.

Café scheduled to open July 2016.
March 6, 2015 Plans have been issued for pricing.

Projected construction start June 2015.

Café scheduled to open July 2016.
February 27, 2015 Plans have been issued for pricing.

Targeting approval at the April Board meeting.

Projected construction start June 2015.

Café scheduled to open July 2016.
February 20, 2015 Plans being finalized to issue for pricing in February.

Projected construction start June 2015.

Café scheduled to open July 2016.

The first phase of moves are scheduled for May 2015.
February 13, 2015 Plans being finalized to issue for pricing in February.

Projected construction start June 2015.

Café scheduled to open July 2016.
February 7, 2015 Renderings were included in Board Meeting presentation January 27.

Plans being finalized to issue for pricing in February.

Projected construction start June 2015.

Scheduled to open July 2016.
January 23, 2015 Updated renderings were presented at Orientation Week sessions.

Projected construction start June 2015.

Scheduled to open July 2016.
January 16, 2015 Updated renderings were presented at Orientation Week sessions.

Projected construction start June 2015.

Scheduled to open July 2016.
January 2, 2015 Projected construction start June 2015.

Scheduled to open July 2016.
December 12, 2014 Projected construction start June 2015.

Scheduled to open July 2016.
December 5, 2014 Approval received on 12/4 to proceed with Construction Documents.

Projected construction start June 2015.

Scheduled to open July 2016.
November 21, 2014 Budget review of Design Development plans continues.

Projected construction start June 2015.

Scheduled to open July 2016.
November 14, 2014 Budget review of Design Development plans is in progress.

Projected construction start June 2015.

Scheduled to open July 2016.
November 7, 2014 Budget review of Design Development plans is in progress.

Projected construction start June 2015.

Scheduled to open July 2016.
October 31, 2014 Design Development plans received on 10/24 for review.

Projected construction start June 2015.

Scheduled to open July 2016.
October 24, 2014 Design Development plans will be complete for review 10/24.

Projected construction start June 2015.

Scheduled to open July 2016.
October 17, 2014 Design Development continues for the Core & Cafeteria; Cafeteria facade design options were presented at the Executive Staff Meeting on 10/13; projected construction start June 2015; Scheduled to open July 2016.
October 10, 2014 Design Development continues for the Core & Cafeteria; projected construction start June 2015; Scheduled to open July 2016.
October 3, 2014 Design Development continues for the Core & Cafeteria; projected construction start June 2015; Scheduled to open July 2016.
September 26, 2014 Design Development continues for the Core & Cafeteria; projected construction start June 2015; Design feedback received from Board; Scheduled to open July 2016.

Proceeding with Schematic Design for the A & B Remodel; Programming for Student Development will continue through 10/1.
September 19, 2014 Review of Schematic Design Cost Estimate continues for the A & B Remodel, Design Development continues for the Core & Cafeteria; projected construction start June 2015.

Programming for Student Development will continue through 10/1.
September 12, 2014 Review of Schematic Design Cost Estimate continues for the A & B Remodel, Design Development is in progress for the Core & Cafeteria; projected construction start June 2015.

Programming for Student Development will continue through 10/1.
September 5, 2014 Review of Schematic Design Cost Estimate continues for the A & B Remodel, Design Development is in progress for the Core & Cafeteria; projected construction start June 2015.

Programming for Student Development will continue through 10/1.
August 29, 2014 Review of Schematic Design Cost Estimate continues for the A & B Remodel, Schematic Design was approved for the Core & Cafeteria; Design Development has begun. Projected construction start June 2015.

Programming continues for Student Development.
August 22, 2014 Review of Schematic Design Cost Estimate is in progress for the A & B Remodel, Design Development is expected to begin within the next week for Core & Cafeteria. Projected construction start June 2015; Programming is in progress for A&B Remodeling including Student Development.
August 15, 2014 Review of Schematic Design Cost Estimate is in progress for Core and Cafeteria, Design Development is expected to begin within the next week. Projected construction start June 2015; Programming is in progress for A&B Remodeling including Student Development.
August 8, 2014 Schematic Design Completed for Core and Cafeteria, Design Development scheduled to begin in next few weeks.

Projected construction start May 2015; Programming is progress for A&B Remodeling.
July 25, 2014 Scope and Budget reconciliation is in progress for projects.

Schematic Design Completed for Core and Cafeteria, Design Development will be proceeding. Projected construction start May 2015.

Programming beginning for A&B Remodeling.
July 18, 2014 Scope and Budget reconciliation is in progress for A&B Core and Cafeteria.

Construction for A&B Core and Cafeteria anticipated - May 2015 – June 2016.
July 11, 2014 Soil Borings for A&B Core and Cafeteria completed 7/10.
June 27, 2014 Scope and Budget reconciliation is in progress for A&B Core and Cafeteria.

Construction for A&B Core and Cafeteria anticipated - Spring 2015.

Soil Borings for A&B Core and Cafeteria to begin - 7/7.
June 20, 2014 Schematic Designs are being evaluated for A&B Core and Cafeteria, pricing for entire project continues.
June 2, 2014 Schematic Design pricing for entire project continues.

Review of design options for entire project continues.

Development of the phasing plan for the A&B Renovations is underway.
May 16, 2014 Detailed pricing review for alignment with approved budget continues; expected completion of review 5/29.

Review of scope to follow detailed pricing review.

Development of design options is underway.
May 9, 2014 Schematic Design pricing for entire project continues.

Review of design options for entire project is in progress.

Development of the phasing plan for the A&B Renovations is underway.
May 2, 2014 Schematic Design pricing for entire project is being developed.

Design for entire project is being reviewed.

Development of the phasing plan for the A&B Renovations continues.
December 20, 2013 The Programming Phase for the Bookstore, Cafeteria, and Student Activities is complete. Meetings will be scheduled as needed for input and approval throughout the various design phases.
December 13, 2013 The Programming Phase for the Bookstore, Cafeteria, and Student Activities are complete.
November 1, 2013 The Cafeteria Committee attended Site Visits at Moraine Valley Community College and Rosalind Franklin University on 10/31. The Kick-Off meeting for Student Activities was held on 10/30.
October 25, 2013 The Cafeteria Committee is scheduled to attend Site Visits at Moraine Valley Community College, Old Orchard-Wilde and Greene, and Rosalind Franklin University on 10/31. The Kick-Off for Student Activities is scheduled for 10/30.
October 18, 2013 The Cafeteria Committee is scheduled to perform Site Visits at Moraine Valley Community College, Old Orchard-Wilde and Greene, and Rosalind Franklin University on 10/31. The Kick-Off for Student Activities is scheduled for 10/30.
October 11, 2013 The Cafeteria Committee performed Site Visits at Joliet Junior College (JJC), Wheaton College, and McHenry County College (MCC) on 10/10. The Bookstore's 2nd Meeting is scheduled for 10/24.
October 4, 2013 The Cafeteria Programming 2nd Meeting was held October 3, 2013. The Bookstore Kick-Off Meeting was held October 3, 2013. The Site Visit for the Cafeteria Committee is scheduled for October 10, 2013.
September 30, 2013 Cafeteria programming kick-off held Sept. 26, 2013. Bookstore and Student Activities Program Committees kick-off next week. Construction starts Summer 2014.
September 23, 2013 Programming starts September 2013.
Construction starts Summer 2014.

Committee Meetings

Meeting Date
Minutes (PDF)
Bookstore Programming Committee
March 18, 2014 Minutes
March 4, 2014 Minutes
December 12, 2013 Minutes
December 5, 2013 Minutes
November 21, 2013 Minutes
November 14, 2013 Minutes
October 24, 2013 Minutes
October 3, 2013 Minutes
Cafeteria Programming Committee
February 27, 2014 Minutes
December 12, 2013 Minutes
December 5, 2013 Minutes
November 21, 2013 Minutes
November 14, 2013 Minutes
October 24, 2013 Minutes
October 3, 2013 Minutes
September 26, 2013 Minutes
Police Programming Committee
June 26, 2014 Minutes
December 12, 2013 Minutes
Student Activities Programming Committee
March 5, 2014 Minutes
November 13, 2013 Minutes
October 30, 2013 Minutes