Parking Lots 2, 3 & 8/Roadway Improvements

Project Description:

This series of projects will resurface, reconfigured, and expand several parking lots on the Grayslake campus. Parking Lot 8, a staff lot located behind the Technology building, will be expanded adding approximately 80 additional staff parking spaces. Lots 2 and 3, two large student lots on the north side of campus will be resurfaced and given lighting upgrades. In addition to the work on the parking lots, a section of Willow Way will be rerouted to pass in front of the PE Center modifying the existing roadway loop around campus.

This lot resurfacing project will grind down the existing asphalt layer and place a newer layer on top. This project will also incorporate the use of bio-swales to assist in filtering out sediment and debris before entering the stormwater system

Budget: $2,234,387

Construction Schedule: April 2014-August 2017

Square footage of new construction: N/A

Square footage of renovated area: N/A

Project Updates

Date
Update
September 19, 2014 The Roadway Expansion project is complete. The roadway is now open.

Willow Way is open between Parking Lot 8 and Lot 2. Access behind the gym is for authorized vehicles only.
September 12, 2014 The Roadway Expansion project is complete. The roadway is now open.

Willow Way is open between Parking Lot 8 and Lot 2. Access behind the gym is for authorized vehicles only.
September 5, 2014 The Roadway Expansion project is nearing completion.

Building 7 east entrance will re-open on 9/6.

Willow Way remains closed for construction between Parking lot 8 and lot 2. Access from the north for roadway behind the gym is available for authorized vehicles only.
August 29, 2014 Completion of the Roadway Expansion project has been delayed due to weather conditions; Anticipated completion is within the next week.

Building 7 east entrance is open.

Willow Way remains closed for construction between Parking lot 8 and lot 2. Access from the north for roadway behind the gym is available for authorized vehicles only.
August 22, 2014 Parking Lot 1 entrance has been moved to South entrance.

Willow Way remains closed for construction between Parking lot 8 and lot 2. Access from the north for roadway behind the gym is available for authorized vehicles only.

Building 7 east entrance will re-open 8/23.

Completion of the Roadway Expansion project has been delayed due to weather conditions; Anticipated completion is within the next 10 days.
August 15, 2014 Parking Lot 1 entrance has been moved to South entrance.

Willow Way remains closed for construction between Parking lot 8 and lot 2. Access from the north for roadway behind the gym will still be available for authorized vehicles only.

Building 7 east entrance remains closed. The North entrance into building 7 will be open for the duration of construction.

Anticipating completion August 22, 2014.
August 8, 2014 Parking Lot 1 entrance has been moved to South entrance.

Willow Way remains closed for construction between Parking lot 8 and lot 2. Access from the north for roadway behind the gym will still be available for authorized vehicles only.

Building 7 east entrance will be closed beginning 8/4. North entrance into building 7 will be open for the duration of construction.

Anticipating completion August 22, 2014.
July 25, 2014 Parking Lot 1 entrance has been moved to South entrance.

Beginning next week - Willow Way will be closed between Parking lot 8 and lot 2. Access from the north for roadway behind the gym will still be available for authorized vehicles only.

Building 7 east entrance will be closed periodically during construction. North entrance into building 7 will be open for the duration of construction.

Anticipating completion August 22, 2014.
July 11, 2014 Roadway Expansion Project Preconstruction Meeting held ‐ 7/8.

Construction of Roadway Expansion - July/August 2014.
June 27, 2014 Roadway Expansion Project, Board Recommendation approved - June 24th Board Meeting.

Construction of Roadway Expansion - July/August 2014.
June 20, 2014 Roadway Expansion Project, Recommendation for Award - June 24th Board Meeting.

Expansion of Parking Lot 8 may be deferred.
June 6, 2014 Lot 8 and Roadway Expansion bids are being evaluated.
June 2, 2014 Bids for Lot 8 and Roadway Expansion were received 5/28.

Expansion of Lot 8 may be deferred.
May 16, 2014 Bids for Parking Lot 8 and Roadway Expansion due 5/21.

Lot 8 will be expanded to include 46 additional spaces.

Lot 6 will be resurfaced; 79-160 fewer spaces during construction.
May 2, 2014 Lot 8 will be expanded to include 46 additional spaces.

Lot 6 will be resurfaced; 79-160 fewer spaces during construction.
April 28, 2014 Lot 8 expansion and roadway construction will be out for bids by May 1, construction is scheduled for this summer. This will include minor renovations to Lots 7 and 7A to accommodate the Science Building construction. Notification of revised traffic patterns will be provided in advance.
April 21, 2014 Lot 8 expansion and roadway construction will be out for bids by May 1, construction is scheduled for this summer. This will include minor renovations to Lots 7 and 7A to accommodate the Science Building construction. Notification of revised traffic patterns will be provided in advance.
April 14, 2014 Lot 8 expansion and roadway construction should be out for bids by May 1, construction scheduled for this summer. This will include minor renovations to Lots 7 and 7A to accommodate the Science Building construction.
April 4, 2014 Design and Engineering is in progress for the Lot 8 expansion, construction scheduled for this summer. Review documents have been distributed to the committee for input and some great feedback about consistency with our sustainability plan.
March 21, 2014 The site planning committee has approved the layout of the Lot 8 Expansion which will be under construction this summer. Modifications will also be implemented in Lot 7 so drivers can navigate safely during the construction of the new Science Building.
March 14, 2014 Concept plans are being developed with input from the Site Programming Committee. Anticipated construction of the expansion to Lot 8 will be summer, 2014.
March 7, 2014 Pavement cores and soil borings for Lots 7&7A Reconstruction / Lot 8 Expansion and Roadway Extension projects were completed on 3/4. Layout concepts were presented and reviewed at the Site Programming Committee Meeting on 3/7.
February 28, 2014 Survey of existing lots' geometry began on Tuesday, February 18.
February 24, 2014 Surveying is in progress for Parking Lots 7&7A Reconstruction / Lot 8 Expansion and Roadway Extension. Conceptual design of Lot 8A meeting to review design schedules was held with McClure on Feb. 28. Layout concepts are being developed.
February 14, 2014 Approval of the updated scope of work to design Lot 8 expansion and roadway extension was received on Feb. 12.
January 31, 2014 Recommendations for award of civil engineering firms to design the reconstruction of Lots 7/7A, and the expansion of Lot 8 were approved at the January 29 Board Meeting.
November 22, 2013 Erikson, Manhard, and McClure were approved at the November Board Meeting as vendors for the Site/Civil Engineering Professional Services project.
November 15, 2013 The Selection Committee for Site/Civil Engineering Professional Services has prepared a recommendation for approval at the November Board Meeting.
November 8, 2013 Review of proposals received for Professional Engineering Services - Site/Civil Engineering, Parking Lots and Roadway Extensions is ongoing.
November 1, 2013 Proposals were received on 10/31 for Request for Proposal (RFP) No. 258: Site/Civil Engineering, Parking Lots and Roadway Extensions.
October 25, 2013 Proposals are due on 10/31 for Request for Proposal (RFP) No. 258: Site/Civil Engineering, Parking Lots and Roadway Extensions.
October 18, 2013 The RFP No. 258 for site/civil engineering, parking lots and roadway extensions was advertised on 10/17. Bid proposals are due 10/31.
October 4, 2013 The second site programming meeting was held on October 3, 2013. Construction anticipated Spring 2014.
September 30, 2013 Site programming kick-off held Sept. 26, 2013. Construction starts Spring 2014.
September 23, 2013 Programming starts September 2013.
Construction starts Spring 2014.