Signage

Project Description:

This project addresses updating the signage and improving way-finding on the Grayslake Campus. Highlights of this project includes updates to the monument signs at Washington Street and Brae Loch Road, replacing the room signs, and design new overhead signage to improve way-finding for interior spaces.

Budget: $752,419

Construction Schedule: March 2016-April 2017

Square footage of new construction: N/A

Square footage of renovated area: N/A

Project Updates

Date
Update
January 27, 2017 Grayslake Campus renumbering is effective.

Installation of permanent room and way‐finding signs is anticipated to be complete by spring break.

Temporary room and way-finding signs are being posted and updated.
December 30, 2016 Grayslake Campus renumbering will be effective January 2017; temporary room and way‐finding signs will be posted.

Installation of permanent room and way‐finding signs is anticipated to be complete by spring break.

Renaming project is to help new students find their way around campus more easily.
December 23, 2016 Grayslake Campus renumbering will be effective January 2017; temporary room and way‐finding signs will be posted.

Installation of permanent room and way‐finding signs is anticipated to be complete by spring break.

Renaming project is to help new students find their way around campus more easily.
December 2, 2016 Grayslake Campus renumbering is expected the begin January 2017.

Renaming project is to help new students find their way around campus more easily.
November 4, 2016 Grayslake Campus renumbering is expected the begin January 2017.
May 20, 2016 Punch list in progress.

Software training is underway.
May 13, 2016 Power has been restored to both signage locations.

Software training is underway.
April 29, 2016 Signage construction is complete, final inspection in progress.

Power to be restored to both sign locations after final inspection.
April 22, 2016 Signage construction is nearing completion.

Power to be restored to both sign locations soon.

Expected completion is late April.
April 15, 2016 Signage construction is nearing completion.

Power to be restored to both sign locations soon.

Expected completion is late April.
April 8, 2016 Signage construction is underway.

Temporary signage is in place at both locations.

Expected completion is late April.
April 1, 2016 Structures for new signs are underway.

Temporary signage is in place at both locations.

Removal of existing signs is complete.

Expected completion is late April.
March 25, 2016 The update work began on the two monument signs this week.

The signs are located at the north end of campus on Washington St. and at the east end of campus at Rt. 45.

Removal of existing signs is complete.

Temporary signage to be completed next week.

Expected completion is late April.
September 18, 2015 Construction scheduled for late-October.

Monument Sign bids received on 8/25, will present at September Board for approval.
September 11, 2015 Construction scheduled for late-October.

Monument Sign bids received on 8/25, will present at September Board for approval.
September 4, 2015 Construction scheduled for late-October.

Monument Sign bids received on 8/25, will present at September Board for approval.
August 28, 2015 Monument Sign bids received on 8/25, will present at September Board for approval.
August 21, 2015 Monument sign bid package has been released, bids due August 25.
August 14, 2015 Monument sign bid package has been released, bids due August 25.
August 7, 2015 Monument sign bid package to be released for bidding next week.
July 31, 2015 Signage consultant has submitted bid documents for monument signs; will go out for bids on 8/7.
July 24, 2015 Signage consultant has submitted bid documents for monument signs for review.
July 17, 2015 New Signage standards and designs for the monument signs were presented at the May Board meeting.

Signage consultant has submitted bid documents for monument signs for review.
July 10, 2015 New Signage standards and designs for the monument signs were presented at the May Board meeting.

Signage consultant has submitted bid documents for monument signs for review.
July 2, 2015 New Signage standards and designs for the monument signs were presented at the May Board meeting.

Signage consultant has submitted bid documents for monument signs for review.
June 26, 2015 New Signage standards and designs for the monument signs were presented at the May Board meeting.

Signage consultant has submitted bid documents for monument signs for review.
June 12, 2015 New Signage standards and designs for the monument signs were presented at the May Board meeting.

Signage consultant to prepare entire standards package and begin bid documents for monument signs.
June 5, 2015 New Signage standards and designs for the monument signs were presented at the May Board meeting.

Signage consultant to prepare entire standards package and begin bid documents for monument signs.
May 29, 2015 New Signage standards and designs for the monument signs were presented at the May Board meeting.
May 22, 2015 New Signage standards and designs for the monument signs were presented at the May Board meeting.
May 15, 2015 New Signage standards and designs for the monument signs have been developed and will be presented at the May Board meeting.

Design concept for renaming buildings to be sequential was distributed for information and feedback.
May 8, 2015 New Signage standards and designs for the monument signs have been developed and will be presented at the May Board meeting.

Design concept for renaming buildings to be sequential was distributed for information and feedback.
May 1, 2015 New Signage standards and designs for the Grayslake Campus monument signs have been developed and were presented to CEOC on April 16. Revised option distributed to signage committee May 1.

New standards and monument sign designs to be presented at the May Board meeting.
April 24, 2015 New Signage standards and designs for the Grayslake Campus monument signs have been developed and were presented to CEOC on April 16.

New standards and monument sign designs to be presented at the May Board meeting.
April 17, 2015 New Signage standards and designs for the Grayslake Campus monument signs have been developed and will be presented to CEOC on April 7.

New standards and monument sign designs to be presented at the May Board meeting.
April 10, 2015 New Signage standards and designs for the Grayslake Campus monument signs have been developed and will be presented to CEOC on April 7.
April 3, 2015 New Signage standards and designs for the Grayslake Campus monument signs have been developed and will be presented to CEOC on April 7.
March 27, 2015 New Signage standards and designs for the Grayslake Campus monument signs have been developed and will be presented to CEOC on April 7.
September 23, 2013 Programming starts April 2014.
Construction starts Fall 2014.