Master Plan Component Project Schedule

View Project Schedule Gantt Chart (PDF)

Project Name Programming Construction Closeout
Science Building Pre 2010 Jan 2014-Dec 2015 Apr 2016
Classroom/Office Doors & Locks May 2013 Aug 2013-Nov 2013 Dec 2013
Classroom Modernizations Sep 2013 Jan 2014-Apr 2014 May 2014
Geothermal Plant & Loop Sep 2013 Apr 2014-Oct 2014 Oct 2014
Parking Lots 2, 3 & 8/Roadway Improvements Sep 2013 Apr 2014-Oct 2014 Nov 2014
Campus Core Projects
(Cafeteria, Bookstore, Student Activities, A&B Courtyard, Main Lobby, Restroom Renovations)
Sep 2013 Jul 2014-Jul 2015 Sep 2015
Lakeshore Campus Building/Renovations Sep 2013 Mar 2015-Apr 2017 Aug 2017
Auto Shop Renovations Sep 2013 Mar 2014-Aug 2014 Sep 2014
Southlake Chemistry Lab Oct 2013 Jun 2014-Sep 2014 Dec 2014
Parking Lots 7 & 7A Jan 2014 Jul 2014-May 2015 Jun 2015
Signage Apr 2014 Oct 2014-Mar 2015 May 2015
Sustainable Agriculture Lab Sep 2014 Mar 2015-Jul 2015 Sep 2015
CNC Lab Renovations Sep 2014 May 2015-Sep 2015 Oct 2015
Student Center (Student Services) Sep 2014 Jan 2016-Jul 2017 Oct 2017
Gym Facade Oct 2014 May 2015-Oct 2015 Nov 2015
A&B Remodel/HVAC
(Common Area Finishes/Furniture, Technology Cabling, Classroom Modernization)
Dec 2014 Dec 2015-Aug 2017 Oct 2017
Wind Turbine Feb 2016 Apr 2017-Aug 2017 Oct 2017
Library Renovations Sep 2016 May 2017-Jul 2017 Aug 2017